Can I Build an ADU in San Diego? Requirements, Permits and Next Steps

Yes, with caveats. This guide covers properties permitted by the City of San Diego. If your residential lot has an existing or planned home, City rules and California law generally allow at least one ADU, and often more. What you can build depends on the type of ADU and your property's conditions.

Small timber and white plaster ADU with a covered deck, set among coastal grasses

San Diego ADU requirements at a glance

San Diego ADU requirements at a glance
Who issues my permit?
Short answer: The City, if your parcel is inside city limits
Where to check: Step 1
What can I build?
Short answer: A detached, attached, conversion or junior ADU (JADU), sometimes several
Where to check: Step 2
Do I have to live there?
Short answer: Not for a standard ADU; rentals must be at least 31 days
Where to check: Step 2
How big can it be?
Short answer: Usually 150 to 1,200 sq ft new; up to 500 sq ft for a JADU
Where to check: Step 3
How close to the property line?
Short answer: Depends on location, height and project type
Where to check: Step 3
Do I need parking?
Short answer: Usually not
Where to check: Step 4
What permits do I need?
Short answer: A building permit, every time
Where to check: Step 5

The City's ADU bulletin, IB400 (opens in new tab), explains the process, and SDMC §141.0302 (opens in new tab) holds the local rules. State law protects some ADUs and overrides conflicting local limits (HCD (opens in new tab)).

Key takeaways

  • A size limit doesn't mean your layout fits. Setbacks, fire separation, stairs and access take space too.

  • Check coastal, fire, parking and older-building conditions early. Each can change what you build or what review you need.

Step 1: Confirm who permits your property

Your mailing address doesn't tell you which rules apply. Your parcel does, identified by its Assessor's Parcel Number, or APN, the County's ID number for that piece of land.

How to look up your parcel

Use the City's zoning portal, ZAPP (opens in new tab):

  1. Search by your address or APN.
  2. Click your parcel, open Parcel Reports and expand the summary sections.
  3. Write down the APN and jurisdiction. Expand Base Zones and Overlay Zones to see your zoning.
  4. Open Layers, then Map Layers, and note whether your parcel falls in any area below, with the date you checked.
The City's ZAPP portal with the search bar, a highlighted parcel and the Parcel Summary panel, numbered 1 to 4
The ZAPP Layers tab with the Map Layers list expanded to show Base Zones and Overlay Zones, numbered 1 to 4
These show how the tool works, not a review of any property.

Layers to note: Coastal Overlay Zone, Beach Impact Area, transit priority area and fire hazard classification. Step 4 explains each. A blank field isn't proof of no restriction, and a survey might be needed, so be sure to go through each step carefully as you get educated on how to prepare your project.

Not in the City of San Diego? Use the County's ADU resources (opens in new tab) or the other city's planning department. Our guide to check whether your property can support an ADU explains the general method.

Your San Diego ADU property-check worksheet

This is the record you'll hand to a designer or the City. Copy the table or download the printable version (opens in new tab); no email address required.

Your San Diego ADU property-check worksheet

Property identification
What to recordAddress, APN and permitting jurisdiction
Existing development
What to recordLegally established homes, garages and other structures, plus permit records
Proposed project
What to recordIntended use, conversion or new construction, rough size and number of units
Mapped conditions
What to recordBase zone and coastal, Beach Impact Area, transit and fire layers
Evidence
What to recordSource link or document, and the date you checked
Open question
What to recordThe specific issue that's still unresolved
Next action
What to recordWho to ask, what to bring and the answer you need

Label each finding Confirmed, Needs confirmation or Problem to look into. The labels describe findings, not approval.

Step 2: Which ADU options and combinations should you investigate?

San Diego allows four kinds of ADU:

Junior

up to 500 square feet inside the home

ADU or JADU?

ADU or JADU?
ADUJADU
KitchenFull kitchenKitchen or efficiency kitchen
BathroomIts ownCan share the main home's
EntranceIts ownIts own outside entrance
Owner occupancyNot requiredGenerally required if it shares a bathroom

Scroll sideways if needed to see every column.

Under Government Code §66333 (opens in new tab), a JADU with its own bathroom doesn't require the owner to live on site. One that shares a bathroom generally does, with exceptions for government agencies, land trusts and qualifying housing organizations. Get the City's Junior Unit Agreement, DS-202A (opens in new tab), before you commit to a rental plan; the City's code and bulletin don't fully match it yet.

How many units can you add?

State law and City rules allow different combinations. Ask your designer which route each unit uses; don't add the totals together.

How many units can you add?
What's on the lotCombination to investigateKey conditions
Single-family home, state routeOne conversion ADU, one JADU and one detached ADUThe detached unit can be up to 800 sq ft of interior livable space, with 4-foot side and rear setbacks.
Single-family home, City routeOne ADU in existing or planned space, one attached or detached ADU, and one JADULocal size, placement and coastal rules apply. More units require the bonus program.
Existing multifamily building, state routeConversions of non-livable space, plus detached ADUsConversions up to 25% of existing units; up to eight detached, but no more than existing units.
Planned multifamily building, state routeUp to two detached ADUsState height limits and 4-foot side and rear setbacks.

Scroll sideways if needed to see every column.

"Multifamily" means attached homes in one building, like a duplex. Several separate houses on one lot don't automatically count. See the HCD ADU handbook (opens in new tab), pages 16 to 18 and 31.

The San Diego ADU bonus program

The City's ADU Home Density Bonus Program lets eligible lots add more ADUs in exchange for renting some at affordable rents for years.

  • Affordable rents: based on 50% of area median income for very-low-income units and 60% for low-income units, each for at least 10 years; 110% for moderate-income units, for at least 15 years.
  • One for one: one market-rate bonus ADU per affordable ADU. Outside a Sustainable Development Area, only one pair.
  • Total caps in single-dwelling-unit zones: four ADUs and JADUs combined on lots up to 8,000 sq ft, five on 8,001 to 10,000 sq ft and six above that. Environmentally sensitive land doesn't count toward lot area.
  • Other requirements: zoning eligibility, fire evacuation access, floor area ratio (FAR), sprinklers and parking.

These are the City's non-coastal rules, in SDMC §141.0302(d) (opens in new tab). Coastal lots differ; see Step 4.

Step 3: What size and layout could fit?

Size. New attached or detached ADUs: generally 150 to 1,200 square feet of gross floor area. Qualifying conversions are exempt from that cap and can add up to 150 square feet for getting in and out. JADUs: up to 500 square feet, not counted toward FAR.

How area is measured. Gross floor area includes the walls; interior livable space, used by some state limits, doesn't. Keep both numbers on your drawings.

Height. City rules apply the zone's height limits and cap detached ADUs in single-dwelling-unit zones at two stories. State-protected detached units are generally limited to 16 feet, or 18 feet in qualifying cases. A second story also needs room for exterior stairs.

Setbacks. A setback is the minimum distance from a property line. Outside the Coastal Overlay Zone:

  • Front: the zone's front setback, with a possible exception for a qualifying 800-square-foot ADU.
  • Street side: 4 feet, or the zone's minimum if smaller.
  • Interior side and rear: outside High and Very High fire zones, you can build to the property line. Above 16 feet, next to a residential property, the minimum is 4 feet.
  • High or Very High fire zone: new construction must sit at least 4 feet from interior side and rear lines.
  • Conversions and same-footprint rebuilds: can keep existing setbacks.

If City rules rule out your design, look at the state route, which can exempt units from local front setbacks, FAR and other standards. The state has challenged parts of the City's ordinance (opens in new tab), so if a rule limits you, ask the City in writing which applies.

Fire separation. This comes from the building code, not zoning. For a typical non-sprinklered home under CRC Table R302.1(1) (opens in new tab), walls less than 5 feet from the line need a one-hour fire rating. No windows or doors are allowed within 3 feet, and from 3 to 5 feet, openings are limited to 25% of the wall.

An ADU footprint is only part of the space you need

Plan of a lot from above: the property boundary, a hatched zoning setback along the lines, a wider fire-separation band, a backyard ADU footprint with exterior stairs, the main home, and a path from the street to the ADU door, numbered 1 to 5
Illustrative, not to scale, not a permit drawing.
An ADU footprint is only part of the space you need
Space on the lotWhat controls itWho checks it
ADU footprintSize limits and how area is measuredDesigner and plan review
Zoning setbackBase zone, City ADU rules or the state routePlanning and zoning review
Fire-separation bandBuilding code limits on walls and openingsBuilding plan review
Exterior stairsZone setbacks and building codeDesigner and plan review
Path from the streetAccess, utility routes and, for bonus projects, evacuation accessDesigner and Fire-Rescue

Scroll sideways if needed to see every column.

Step 4: Which property conditions could change the plan?

Your ZAPP lookup shows which of these apply.

Coastal location

In the Coastal Overlay Zone, you may need a Coastal Development Permit, even to convert a garage. Note whether your lot is in the appealable area, where decisions can go to the California Coastal Commission.

Coastal rules also lag. Per the City's adoption register (opens in new tab), Housing Action Package 2.0 reached the coast March 11, 2026, but the 2025 and 2026 ADU amendments still await coastal certification, so don't assume the newer bonus caps apply there.

Next step: ask ADUs, Planning and Zoning which permit process and rules version governs your project.

Fire hazard zone

The City's fire map, effective August 30, 2025, raises some State Moderate or High areas to Very High, so use the City map. Expect review of wildfire-resistant construction and defensible space.

Next step: save your result from the City fire map (opens in new tab) and ask Fire-Rescue about materials, brush management and access before choosing a location.

Parking and garage conversions

Most standard ADUs don't need parking. The main exception is a Beach Impact Area lot outside a transit priority area, which may need one space unless the ADU is 500 square feet or less. Replacing parking lost in a garage conversion is a separate question, and bonus units outside a transit priority area have their own rule. If a conversion leaves your curb cut out of compliance, the City can require you to close it.

Next step: measure and photograph your driveway, then ask Right-of-Way Permits what the conversion triggers.

Older buildings

Work on a parcel with any structure 45 years or older, including a garage, can trigger historical screening. Interior-only work is exempt, and age alone doesn't make a building historic. See the City's review of buildings over 45 years old (opens in new tab).

Next step: bring building records, exterior photos and your scope to a Historical Resources appointment.

Utilities, slopes and easements

Ask early about electrical capacity (SDG&E (opens in new tab)), the sewer tie-in and water service (IB166 (opens in new tab)). Qualifying conversions generally don't need new connections. A title review finds easements; slopes may need survey and soils work.

Next step: ask for a utility determination for your project rather than assuming shared or separate meters.

For what these conditions mean for your budget, see ADU costs in San Diego.

How one finding changed this Example ADU Plan

How one finding changed this Example ADU Plan
Original proposal (2021 public pilot)FindingSupporting evidenceResulting design or scope decisionRemaining uncertainty
A studio ADU at a San Diego Housing Commission propertySite slopes required changes after construction beganSDHC pilot report, page 23 (opens in new tab)Drawings were revised and resubmitted to the CityThe report doesn't isolate the exact redesign or delay

Scroll sideways if needed to see every column.

Step 5: What permits and documents will you need?

Every ADU and JADU needs a building permit. A typical sequence:

  1. Confirm your scope and extra approvals

    such as coastal, historical and right-of-way.

  2. Prepare your submission

    site and floor plans, elevations, structural documents, energy calculations and forms.

  3. Apply online

    through the City's Development Services Application Portal, choosing Building Construction. Follow IB400's instructions (opens in new tab).

  4. Respond to comments

    on completeness and plan review.

  5. Meet the conditions for issuance

    such as fees and required agreements.

  6. Build, pass inspections and get occupancy sign-off

    before anyone moves in.

Under Government Code §66317 (opens in new tab), the City generally has 15 business days to say whether your application is complete and 60 days to approve or deny a complete one. These are review deadlines, not construction timelines.

Fees. For what to budget for permit, school and utility fees, see permits and local fees in our San Diego ADU cost guide.

Preapproved plans

The City's ADU resources (opens in new tab) point to preapproved plans from the County, Chula Vista and Encinitas. Ask about licensing and current-code compatibility. City master plans can expire when a new building code takes effect (IB114A (opens in new tab)), and every plan still needs a site plan and review.

How do you get an answer about your specific property?

DSD appointments (opens in new tab) can be a helpful resource. Book an appointment for help explaining the process.

Who to ask, what to bring and what to obtain

Who to ask, what to bring and what to obtain
Unresolved questionExact routeBring and askExpected result
Which rules apply to my ADU?ADUs, Planning and ZoningAPN, ZAPP findings and your idea. Ask which provisions apply.Orientation and the right review route
Do I need historical review?Historical ResourcesBuilding ages, photos and changes. Ask what's needed.Required records and route
Does my driveway have to change?Right-of-Way PermitsSite sketch and driveway measurements. Ask what work is triggered.Procedure and scope
I need a written answer about this layout.Preliminary Review, IB513 (opens in new tab)Drawings and focused code questionsWritten responses
What does a plan-check comment mean?Your assigned reviewerProject number, the comment and your proposed fixWhat resolves it

Scroll sideways if needed to see every column.

A script to adapt: "I'm considering a [project type] at APN [number]. ZAPP shows [condition], but I need to know [issue]. What should I bring?"

Preliminary Review costs $1,588.73 for one discipline or $12,983.99 for several (checked October 7, 2026), so save it for a question you can't resolve another way.

See what fits your property

Answer a few questions and the ADU planner shows what you can likely build at your address, what it would cost all-in and the local rules that decide it. When you’re ready, it can introduce you to a Wonderly contractor.

ADU Planner

Frequently asked questions

Can I convert my garage into an ADU?

Often, yes. Check whether the conversion qualifies, the garage's permit history, historical screening if it's 45 years or older and, near the coast, parking.

Can I build a two-story ADU?

Possibly. Check the height limit that applies, the side and rear setbacks and where stairs would go, all together.

Do I have to live on the property?

Not for a standard ADU. A JADU that shares the main home's bathroom generally requires it; one with its own bathroom doesn't.

Do preapproved plans mean my property is approved?

No. A preapproved plan covers the building design. Your site and application still need review.

How much does an ADU permit cost in San Diego?

There's no single number. Ask for an estimate that separates permit, impact, school and utility charges, starting with the City's fee schedule, IB501 (opens in new tab). Our guide to ADU costs in San Diego covers the full budget.

Why trust this guide

Wonderly helps homeowners plan ADUs with trusted local builders; this guide draws on real projects, official sources, and expert review.

Data you can check

Every cost, rule, and timeline links to its source, whether official city code, published pricing, or real builder proposals. Every page explains how we calculate every estimate and range.

Reviewed by experts

A named ADU builder, architect, or expert reviews each guide. We show their credentials, the date reviewed, and what still needs local verification.

Plan your own ADU

Our ADU planner uses this same data and method to turn your exact address and personalized goals into options, costs, and local rules for your specific property.